2013年6月29日星期六

Microsoft 070-178 exam practice questions and answers

Microsoft 070-178 certificate can help you a lot. It can help you improve your job and living standard, and having it can give you a great sum of wealth. Microsoft certification 070-178 exam is a test of the level of knowledge of IT professionals. IT-Tests.com has developed the best and the most accurate training materials about Microsoft certification 070-178 exam. Now IT-Tests.com can provide you the most comprehensive training materials about Microsoft 070-178 exam, including exam practice questions and answers.


The trouble can test a person's character. A bad situation can show special integrity. When to face of a difficult time, only the bravest people could take it easy. Are you a brave person? If you did not do the best preparation for your IT certification exam, can you take it easy? Yes, of course. Because you have IT-Tests.com's Microsoft 070-178 exam training materials. As long as you have it, any examination do not will knock you down.


Whole IT-Tests's pertinence exercises about Microsoft certification 070-178 exam is very popular. IT-Tests's training materials can not only let you obtain IT expertise knowledge and a lot of related experience, but also make you be well prepared for the exam. Although Microsoft certification 070-178 exam is difficult, through doing IT-Tests's exercises you will be very confident for the exam. Be assured to choose IT-Tests.com efficient exercises right now, and you will do a full preparation for Microsoft certification 070-178 exam.


IT-Tests's products can not only help you successfully pass Microsoft certification 070-178 exams, but also provide you a year of free online update service,which will deliver the latest product to customers at the first time to let them have a full preparation for the exam. If you fail the exam, we will give you a full refund.


Exam Code: 070-178

Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)

With IT-Tests.com's Microsoft 070-178 exam training materials, you can get the latest Microsoft 070-178 exam questions and answers. It can make you pass the Microsoft 070-178 exam. Microsoft 070-178 exam certification can help you to develop your career. IT-Tests.com's Microsoft 070-178 exam training materials is ensure that you fully understand the questions and issues behind the concept. t can help you pass the exam easily.


IT-Tests.com has a huge IT industry elite team. They all have high authority in the IT area. They use professional knowledge and experience to provide training materials for people ready to participate in different IT certification exams. The accuracy rate of exam practice questions and answers provided by IT-Tests.com is very high and they can 100% guarantee you pass the exam successfully for one time. Besides, we will provide you a free one-year update service.


070-178 (Microsoft Project 2010, Managing Projects) Free Demo Download: http://www.it-tests.com/070-178.html


NO.1 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D

Microsoft   070-178 demo   070-178 certification training

NO.2 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD

Microsoft   070-178 test   070-178 original questions

NO.3 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C

Microsoft   070-178   070-178   070-178 demo   070-178 questions

NO.4 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A

Microsoft questions   070-178 test questions   070-178   070-178 exam prep   070-178

NO.5 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C

Microsoft test questions   070-178 study guide   070-178   070-178

NO.6 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C

Microsoft   070-178 certification training   070-178   070-178   070-178

NO.7 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C

Microsoft   070-178   070-178 exam dumps   070-178

NO.8 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C

Microsoft   070-178 exam dumps   070-178 certification   070-178

NO.9 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C

Microsoft   070-178   070-178   070-178

NO.10 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D

Microsoft   070-178 exam   070-178   070-178 certification training   070-178 braindump

IT-Tests.com provide different training tools and resources to prepare for the Microsoft 070-178 exam. The preparation guide includes courses, practice test, test engine and part free PDF download.


没有评论:

发表评论