2013年8月28日星期三

Microsoft certification 70-178 exam targeted exercises

IT-Tests.com provide different training tools and resources to prepare for the Microsoft 70-178 exam. The preparation guide includes courses, practice test, test engine and part free PDF download.

According to the research of the past exams and answers, IT-Tests.com provide you the latest Microsoft 70-178 exercises and answers, which have have a very close similarity with real exam. IT-Tests.com can promise that you can 100% pass your first time to attend Microsoft certification 70-178 exam.

In recent years, fierce competition agitates the forwarding IT industry in the world. And IT certification has become a necessity. If you want to get a good improvement in your career, The method that using the IT-Tests.com’s Microsoft 70-178 exam training materials to obtain a certificate is very feasible. Our exam materials are including all the questions which the exam required. So the materials will be able to help you to pass the exam.

Now it is a society of abundant capable people, and there are still a lot of industry is lack of talent, such as the IT industry is quite lack of technical talents. Microsoft certification 70-178 exam is one of testing IT technology certification exams. IT-Tests.com is a website which provide you a training about Microsoft certification 70-178 exam related technical knowledge.

IT-Tests.com's Microsoft 70-178 exam training materials is virtually risk-free for you at the time of purchase. Before you buy, you can enter IT-Tests.com website to download the free part of the exam questions and answers as a trial. So you can see the quality of the exam materials and we IT-Tests.comis friendly web interface. We also offer a year of free updates. If you do not pass the exam, we will refund the full cost to you. We absolutely protect the interests of consumers. Training materials provided by IT-Tests.com are very practical, and they are absolutely right for you. We can make you have a financial windfall.

IT-Tests.com is a very good website to provide a convenient service for the Microsoft certification 70-178 exam. IT-Tests's products can help people whose IT knowledge is not comprehensive pass the difficulty Microsoft certification 70-178 exam. If you add the Microsoft certification 70-178 exam product of IT-Tests.com to your cart, you will save a lot of time and effort. IT-Tests's product is developed by IT-Tests's experts' study of Microsoft certification 70-178 exam, and it is a high quality product.

Exam Code: 70-178
Exam Name: Microsoft Microsoft Project 2010, Managing Projects 70-178
Free One year updates to match real exam scenarios, 100% pass and refund Warranty.
Updated: 2013-08-28

If you have a faith, then go to defend it. Gorky once said that faith is a great emotion, a creative force. My dream is to become a top IT expert. I think that for me is nowhere in sight. But to succeed you can have a shortcut, as long as you make the right choice. I took advantage of IT-Tests.com's Microsoft 70-178 exam training materials, and passed the Microsoft 70-178 exam. IT-Tests.com Microsoft 70-178 exam training materials is the best training materials. If you're also have an IT dream. Then go to buy IT-Tests.com's Microsoft 70-178 exam training materials, it will help you achieve your dreams.

70-178 (Microsoft Project 2010, Managing Projects) Free Demo Download: http://www.it-tests.com/70-178.html

NO.1 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C

Microsoft exam   70-178   70-178 study guide   70-178 certification training   70-178 braindump

NO.2 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D

Microsoft   70-178 demo   70-178 braindump   70-178

NO.3 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C

Microsoft   70-178   70-178   70-178 original questions

NO.4 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C

Microsoft   70-178   70-178

NO.5 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D

Microsoft study guide   70-178   70-178 test   70-178   70-178 braindump

NO.6 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD

Microsoft exam prep   70-178 pdf   70-178   70-178 original questions

NO.7 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A

Microsoft   70-178   70-178 original questions   70-178 original questions   70-178 answers real questions

NO.8 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C

Microsoft demo   70-178   70-178 original questions   70-178

NO.9 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C

Microsoft exam simulations   70-178 pdf   70-178 study guide   70-178 exam

NO.10 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C

Microsoft exam prep   70-178   70-178   70-178

Microsoft 70-178 is one of the important certification exams. IT-Tests's experienced IT experts through their extensive experience and professional IT expertise have come up with IT certification exam study materials to help people pass Microsoft Certification 70-178 exam successfully. IT-Tests's providing learning materials can not only help you 100% pass the exam, but also provide you a free one-year update service.